BIM & Virtual Construction, Honam High Speed Railway Lot No. 1-1

고객사 : SK E&C

계약기간 : 2012-12

BIM’s information model was applied to new Railway Bridge crossing the existing railway bridge for KTX. Taesung S&I made a BIM based design from existing 2D based design. The detailed construction time schedule is made using the equipment simulation of BIM. Based on the results of this process and deliverables production, we get following purposes:
 Completion of detailed Construction Time Schedule. /Review of Safety Measure.
 /Proper Estimation of Equipment Capacity for installation. /Comparing 3D BIM with 2D based design.
 3D BIM equipment simulation was used to make the detailed construction time schedule and estimate the proper equipment capacity for constructing bridge.